EV Chargers

Single family homes

Available for single-family residences using the city-provided eligibility checklist and forms. To apply:

Step 1.Complete forms

Complete the eligibility checklist, guide to EVSE and the EVSE load calculation worksheet.

Step 2.Log in/create account

Submit the application online by selecting the “EVCS” permit.

Step 3.Submit forms

Upload the required forms and submit your permit application.

Step 4.Get your permit

Estimated processing time: 1-3 business days.

 

All other locations

For all other EV charger installations. To apply:

Step 1.Submit information

Submit a site plan, service load calculations, a single-line diagram and product specifications.

Step 2.Create account/log in

Select “EVCS” permit type and upload the necessary documents.

Step 3.Get your permit

Estimated processing time: 5-10 business days.